Pin and Hanger Bridge Assembly Rehabilitation

Project Details

Location: Hartford, CT
Completion Date: In Progress
Project Type: Bridge Construction/Rehabilitation - Industrial Hazardous Paint Removal (SSPC-QP2 Certified) - Field Application of Coatings on Complex Structures (SSPC QP1 Certified)
Overall Length: Up to 4211 ft.
Main Span Length: Up to 250 ft.
Primary Materials: Steel
Total Project Value: $6,183,300
SUMMARY

The project consists of replacing the existing pin and hanger assemblies with new stainless-steel assemblies to extend the service life of the bridge. The work includes jacking the bridge girders, removing the existing pin and hanger assemblies, line boring the connection holes, installing the new stainless-steel assemblies, abrasive blast cleaning and painting the beam ends, and applying the final topcoat within the designated painting limits. The project also includes structural steel repairs at both bridge locations.

Key Challenges

A significant challenge on the project involved managing extended lead times for critical stainless-steel components and addressing unforeseen site conditions. ROTHA worked closely with the project team to navigate these challenges, implement the necessary change orders, and keep the project moving forward.

Partner with ROTHA

ROTHA works with public agencies and private clients on a wide range of heavy civil projects. Regardless of the project’s scope or complexity, we bring the same commitment to planning, coordination, and delivering quality results.